All Projects
Falmouth Drill Project
Location
Falmouth, ME
Services Performed
Horizontal Directional Drilling
Our Scope
Installed over 300 feet of 8” HDPE gravity storm drain across an active shopping center parking lot, including beneath two major travel ways, multiple parking areas, and landscaped islands. Work was completed using the Arrowbore system to achieve installation accuracy within 0.20’ of the designed line and grade while maintaining normal traffic patterns and uninterrupted public access throughout construction.